    Douglas Water - Construction Diary

Construction of the scheme began in June 2006. The approximate timeline for the different construction phases was:

  • June and July 2006
    Preparation of the pipeline easement.
  • August - September 2006
    Installation of pipeline.
  • November 2006
    Excavation for the powerhouse commenced.
  • March 2007
    Works at intake site commenced with the construction of a river diversion.
  • June 2007
    Construction of intake structure began.
  • October 2007
    Pipeline pressure test completed.
  • February 2008
    Grid Connection.
  • April 2008
    First generation.