Douglas Water - Construction Diary
Construction of the scheme began in June 2006. The approximate timeline for the different construction phases was:
- June and July 2006
Preparation of the pipeline easement.
- August - September 2006
Installation of pipeline.
- November 2006
Excavation for the powerhouse commenced.
- March 2007
Works at intake site commenced with the construction of a river diversion.
- June 2007
Construction of intake structure began.
- October 2007
Pipeline pressure test completed.
- February 2008
Grid Connection.
- April 2008
First generation.