Home
Search
 
    Construction update - June 2008

Construction overview

  • Scour protection work, which began in April 2008 is progressing to schedule.
  • Offshore foundation work is now over half way through, in preparation for the installation of the turbine towers and Nacelles (the hub and blades) later this year (2008).
  • Onshore preparation works are underway to bring the power generated by the wind farm on land, and connect it to the local energy distribution network.
Offshore construction work progress
  • At the time of publication, we are over half way through the foundation installation works. Fifteen (15) of the 25 Rhyl Flats Offshore Wind Farm's foundations have been successfully installed.
  • Each foundation is a steel monopile, up to 40m long, 4.7m wide and topped with a yellow transition piece.
  • Scour protection work, to protect the foundations, continues alongside the foundation piling works.
  • Progress remains on schedule.
Onshore construction work progress
  • Construction of the substation at Towyn is almost complete with mechanical erection of the electrical equipment ongoing
  • The Grid transformer has been delivered and installed at the sub-station
  • Cable civil works are complete and cable pulling/installation is ongoing
  • Beach works to receive the offshore cable are ongoing
  • Offshore cable installation, to bring the power onshore is scheduled to begin in July 2008.
Construction diary milestones
  • Offshore foundation works are expected to be finished by end of summer 2008.
  • Scour protection is due to finish by the end of August 2008.
  • The first of the 25 wind farm turbines is due to be installed and generating clean, green energy by the end of 2008.
  • Rhyl Flats offshore wind farm is expected to be fully constructed and operational by summer 2009.
(*All dates are continually subject to the impacts of weather conditions and progress.)

back top


Construction Newsletter

sitemap disclaimer